North-South Road (CAREC), risks identified and issues for monitoring

North-South Road (CAREC), risks identified and issues for monitoring

Plot Phase Donor (MFI) Contractor Identified risks and issues for monitoring
Aral – Kazarman (km 195–291) Phase II Export-Import Bank of China China Road and Bridge Corporation (CRBC) Criminal case of the State Committee for National Security of the Kyrgyz Republic (from April 14, 2023): overestimation of the cost and scope of work, possible damage to the state
Balykchy – Kochkor (0–43 km) Phase III ADB | Asian Development Bank (ADB) JV Sinohydro Corporation Ltd. (PRC) risks/check points
Kochkor – Epkin (km 62.4–89.5) Phase III ADB | Asian Development Bank (ADB) JV Sinohydro Corporation Ltd. (PRC) risks/check points
Epkin – Bashkuugandy (89–159 km) Phase III ADB | Asian Development Bank (ADB) Todini Costruzioni Generali S.p.A. → China Railway No. 5 Engineering Group Co. Ltd. (CR5) Termination of contract with Todini; replacement of contractor; delays and cost/volume revisions.

The Todini contract was concluded in 2018 and terminated on 12/01/2020 after approximately 9.5% of the work was completed. The new contract with CR5 was concluded on September 23, 2021; construction substantially completed on 11/30/2024.

Bashkuugandy – Kyzyl-Zhyldyz (159–183 km) Phase III Islamic Development Bank + Saudi Fund for Development JV MOST Group + China Road and Bridge Corporation Complex co-financing; Co-financing and contract structure require separate monitoring.
Kyzyl-Zhyldyz – Aral (km 183–195) Phase I Export-Import Bank of China CRBC Safety of mountain areas; slope stability and landslide protection; security of the Kok-Art tunnel; compliance with design decisions; CRBC contractor warranty; additional security costs; quality and durability of road infrastructure; environmental and social consequences.
Kazarman – Jalal-Abad (km 291–433) Phase I Export-Import Bank of China CRBC